用于支撑海上风电机的挪威Hywind浮动平台的安装和工作原理

已有 4925 次阅读 2019-3-6 17:56 |系统分类:海外观察| 浮动平台, 风电机

世界上第一座海上浮动式风电场于2017年在英国北海建成,由5台6MW Hywind浮动式风电机组成。据挪威公司称,十年后它的技术将使发电成本降低至相当人民币0.3-0.5元。说实话,这类设备在今天的中国生产制造,发电成本一下子就会降下去。他们只是在等待十年后在印度越南那样的国家制造吧。其中的原因,只要想一想太阳能发电技术发展生产的过程你们就会理解了。

下面是挪威公司对Hywind浮动平台的安装和工作原理的简介,实质上这浮动平台也就这么简单。


How Hywind works

Hywind is a floating wind turbine design based on a single floating cylindrical spar buoy moored by cables or chains to the sea bed. Its substructure is ballasted so that the entire construction floats upright. Hywind combines familiar technologies from the offshore and wind power industries into a new design. 

hywind-wind-farm-illustration-16-9.jpg

Hywind Scotland. Illustration / Equinor

The floating design allows Hywind wind turbines to be placed in waters too deep for conventional bottom-fixed turbines. Offshore winds are typically more consistent and stronger over the sea, due to the absence of topographic features that disrupt wind flow.

Hywind uses a ballasted catenary layout with three mooring cables with 60 tonne weights hanging from the midpoint of each anchor cable to provide additional tension.

Control software on board constantly monitors the operation of the wind turbine and alters the pitch of the blades to effectively dampen the motion of the tower and maximise production. Electricity produced is taken to shore through cables.

After 8 years of testing a full-scale prototype offshore Karmøy in Norway, the Hywind demo has been shown to function well in all wind and wave conditions.

Hywind Stord assembly plant

The neighbors of the shipyard Kværner Stord are used to having oil platforms and rigs in view. But the assembly of Hywind has really changed the scenery. (Photo: Odd Henning Gilje/NSG)

SUBSTRUCTURE

The floating structure consists of a steel cylinder filled with ballast water and rock or iron ore. An updated design has been made based on the experience from the demonstrator prototype. The new design has a design draft of 85-90 m and a displacement of around 12,000 tonnes. The diameter at the water line is about 9-10 m, while the diameter of the submerged section of the buoy is 14-15 m. 

FABRICATION:

Onshore assembly reduces time and risk of offshore operations. The substructures for Hywind Scotland were transported in a horizontal position to the onshore assembly site at Stord on the west coast of Norway. There, the giant spar-structures were filled with close to 8000 tonnes of seawater to make them stay upright. Finally, they were filled with around 5500 tonnes of solid ballast while pumping out approximately 5000 tonnes of seawater to maintain draft.

hywind-scotland-mooring-chains-16-9.jpg

Mooring chains. (Photo: Eva Sleire)

MOORING SYSTEM:

The structure is moored to the seabed using a conventional 3-line mooring system. In a wind farm layout, common anchor points may be used, reducing the number of anchors per unit. The mooring lines are currently made of steel chains. In future, anchor types will be determined by seabed conditions, and in the case of Hywind Scotland, suction anchors are used.

In 2009 Statoil installed the Hywind Demo offshore Karmøy, Norway. The demonstration unit has a 2,3 MW turbine, while the diameter of the blades is 85 meters. For six years, the demonstration unit performed well, and in 2015 it was decided to proceed to the next phase. 

HYWIND FACTORY

Equinor has a strong cost reduction ambition for Hywind. We will utilize a “Hywind Factory” methodology to realise our amibiton. The “Hywind Factory” is not a physical factory, but rather a systematic approach to mature and industrialize the Hywind concept, to significantly reduce costs and improve the competitiveness of floating wind.

Key focus areas of the Hywind Factory include:

  • Optimising the Hywind substructure with respect to material use and production friendliness, adapting it to volume production.

  • Design Hywind to be compatible with important trends in the bottom-fixed industry through the use of standard turbines, standard installation vessels and so forth.

  • Working to standardize solutions that are common to the floating wind industry, such as mooring and anchoring and export cables.  

DIMENSION

HYWIND DEMO
2.3 MW
KARMØY, NO
HYWIND SCOTLAND
6.0 MW
BUCHAN DEEP, UK

Mass

5300 tonnes

11200 tonnes

Draught

100 m

78 m

Hub height

65 m

98 m

Water depth

220 m

105 m

Substructure Diameter

8.3 m

14.4 m

Rotor diameter

85 m

154 m

Anchor

Drag embedded anchorSuction anchor

Mooring

Wire/chainChain




https://blog.sciencenet.cn/blog-2548156-1166056.html

上一篇:处理生活垃圾焚烧产生的飞灰的最好方法
下一篇:值得思考的问题
收藏 IP: 83.226.176.*| 热度|

2 杨正瓴 魏焱明

该博文允许注册用户评论 请点击登录 评论 (0 个评论)

数据加载中...
扫一扫,分享此博文

Archiver|手机版|科学网 ( 京ICP备07017567号-12 )

GMT+8, 2024-3-29 05:40

Powered by ScienceNet.cn

Copyright © 2007- 中国科学报社

返回顶部